a Microsoft Project plan for a patient information management system.

Create the Admission, Discharge, and Transfer Module (requires subtask I, configuration period: 25 days, training period: 10 days)
Subtask I: Create the Patient Registration Module (requires subtask II, configuration period: 4 days, training period: 4 days)
Subtask II: Create the Master Patient Index (configuration period: 4 days)
Subtask III: Create the Patient Scheduling Module (requires subtask II, configuration period: 7 days, training period: 15 days)

 